Thursday, April 29, 2010

April 29, 2010

They were supposed to pour the foundation today, but the plumber didn't call in the necessary inspections. They might pour the foundation tomorrow if weather permits.

All of the slab plumbing and electrical are installed.





The diagonal PTEX pipe is for an outdoor faucet


All of the pipes/conduits have Termimesh on them to keep termites out.


PTEX water pipes for the kitchen


The house next door is gone and they're already working on the foundation.